Standard proforma estimates for construction of departmental buildings

Sl. No.
Name of building
Plinth area (sq. m)
Estimate (Rs.)
Tawang, Kurungkumey, Mouling, Yingkiong, Anini, Anjaw, Kamlang, Daporijo, Mechuka, Tuting

Bomdila, Shergaon, Seppa, Hapoli, Along
Others
1
4 unit Barrack
157.97
30,12,100
26,64,600
23,17,000

2
SPT I
36.09
10,08,400
8,92,100
7,75,700

3
SPT II
43.29
13,13,000
11,62,200
10,10,600

4
SPT III
52.6
15,19,400
13,44,100
11,68,800

5
SPT IV
84.55
22,95,300
20,30,400
17,65,600

6
RANGE OFFICE

51.29
12,61,200
11,15,600
9,70,100

7
BEAT OFFICE
31.39
7,81,900
6,91,700
6,01,400


FRH : PLINTH AREA
SMALL FRH = 1 TYPE IV
MEDIUM FRH = 1 TYPE IV + 1 TYPE II
LARGE FRH = 2 TYPE IV  

DETAILED ESTIMATE:
  1. 4 unit Barrack
  2. SPT I
  3. SPT II
  4. SPT III
  5. SPT IV
  6. RANGE OFFICE
  7. BEAT OFFICE