PRESENT STATUS OF ALL FOREST DIVERSION PROPOSALS

Sl. No.
Name of Project
Area proposed (ha)

Stage of Approval
Government Order No.
1
O-S-K-R-T ROAD
km 82 to km 92.0
9.00
Final approval
3ANC-078/2008-SH-1/1392-93 dated 04.09.09

2
O-S-K-R-T ROAD
km 92 to 105.525 km
14.46
Final approval
3ANC-138/2008-SH1/2879-80 dated 25.02.10

3
O-S-K-R-T ROAD
km 105.252 to 114.125.00 km
8.64
Forwarded to PCCF Office
-
4
O-S-K-R-T ROAD
km 114.125.00 to 122.625 km
9.77
In principle approval
3-ANC 093/2011-SHI/2319-19 dated 23.11.11
5
O-S-K-R-T ROAD
km 120 to 134.805 km
18.282
Final approval
3ANC-087/2008-SH-1/1411-12 dated 04.09.09

6
O-S-K-R-T ROAD
km 134.805 to 146.805 km
14.802
Final approval
3ANC/122/2007-SH1/2589-90 dated 02.02.10

7
O-S-K-R-T ROAD
km 146.805 to 159.48 km
23.4075
Final approval
3ANC/123/2007-SH1/1409-10 dated 04.09.09
8
Shergaon –Morshing Road km 00.00 to 15.925 km 

9.555
Final approval
3ANC/022/2007-SH1/2157-58 dated 21.12.09
9
132 KV Balipara-Tenga Transmission line

45.50
Final approval
-
10
Shergaon –Doimara Road km 0 - 28.00 to 72.00 km 
38.40
Final approval
3ANC/111/2008-SH1/1308-09 dated 10.08.11
11
B-C-T ROAD
km 50.00 to 65.00 km 
8.85
Forwarded to CCF Office on 07.01.2012

-
12
BCT ROAD
Km 88.00 to 102.625 km 

24.7125
Forwarded to PCCF Office
-
13
B-C-T ROAD
km 99.45 to 106.38 km

9.77
Forwarded to PCCF Office
-
14
OSKRT 58.00 km to 81.00 km
22.44 ha
Forwarded to CCF Office on 28.05.11

-